As reported at the
last meeting, the diversion of Footpath 1 in the New Playing
Field is progressing and although the anticipated date for
completion of the legal matters is anticipated for June 2008,
I feel this date may be exceeded as the matter of the location
of the exit to the road is still not finally settled. The
County Council have suggested that an opening (they will not
agree to a stile) be made in the hedge adjacent to the car
park entrance. I have argued that this is pointless as there
is already a gap in the fence to the car park and will create
another hazard. John Ball, Kerrier’s Solicitor is therefore to
proceed as agreed at your last meeting. I have no further
progress to report.
I reported to your
last meeting on a letter from the County Council re Tretheague
Bridge but there has still been no response as regards Kennall
Bridge. I shall write again following the meeting.
The schedule for the
maintenance of fingerposts and milestones has been updated and
will be issued asking for quotes from three if not four
suppliers of this service as soon as the Clerk is able. To
date, this has still not been possible.
As reported at the
last meeting, Mr Fletcher had offered dates for a meeting
about footpaths. Unfortunately, the Clerk has been unable to
rearrange this meeting due to other commitments.
I have heard nothing
further from Mrs Penrose concerning Footpath 7.
No progress with Mill
Lane and the planings because the Clerk has still not had time
due to other commitments.
The fence at
Tresevern Croft has not been repaired by SWW but in view of
comments made by their new Ranger at the February meeting, it
may be some time before action is taken. Nevertheless I feel a
reminder is due and this will be sent following the meeting.
I have now had an
acknowledgement to the letter sent to the County Council
concerning the adoption of street lights. I have been promised
a definitive answer re the adoption of the two lights at
Longdowns before the meeting and will report further then.
As reported to the
last meeting, an order has been issued by Coastline housing
for the works in Crellow Hill to be done but I have no
knowledge as to whether the work has been carried out..
As previously
reported, the Environment Agency have agreed that the old
channel of the river at Foundry where it runs through the
gardens of Tremenhere and Riverside is part of the enmained
river and their duty to maintain and repair. Mr Newing was
seeking confirmation of this in writing from EA and the Clerk
has not as yet heard whether this has been forthcoming,
although Mr Newing has again asked them. I have nothing
further to report at present and will send another reminder
following the meeting.
The state of the
muddy area at the entrance to Odette Eddy’s land from FP 7 has
improved. Whether this is due to something she has done or the
weather is indeterminate!
At the end of May,
Cllr J Biscoe emailed Cllr Ms J Tisdale, as assistant
Portfolio Holder, details of the portfolio and, with the
assistance of the Clerk, she intends to look into the
portfolio and provide a more detailed report for next month.